IG5336.9201-ch4-2




ATTACHMENT 2
Ellsworth AFB MACC & TO

Section B - Supplies or Services and Prices
|
|
|
|
|
|
ITEM NO
|
SUPPLIES/SERVICES
|
QUANTITY
|
UNIT
|
UNIT PRICE
|
AMOUNT
|
0001
|
|
1
|
Lot
|
$100,770.00
|
$100,770.00
|
|
|
Base Bid
FFP
Base bid shall include all items of work as outlined in the Task Order and Statement of Work to Repair Handicap Access to Bldg 1007
NSN: Z199-95-CES-MACC
MILSTRIP: FQ469043070400
PURCHASE REQUEST NUMBER: FQ4690430704
SIGNAL CODE: A
|
|
|
|
|
|
|
|
|
|
|
|
|
NET AMT
|
$100,770.00
|
|
|
|
|
ACRN AA Funded Amount
|
|
$100,770.00
|
FOB: Destination
|
|
|
|
|
|
ITEM NO
|
SUPPLIES/SERVICES
|
QUANTITY
|
UNIT
|
UNIT PRICE
|
AMOUNT
|
0002
|
|
1
|
Lot
|
$990.00
|
$990.00
|
|
|
Investigative Costs
FFP
Investigative Costs
NSN: Z199-95-CES-MACC
MILSTRIP: FQ469043070401
PURCHASE REQUEST NUMBER: FQ4690430704
SIGNAL CODE: A
|
|
|
|
|
|
|
|
|
|
|
|
|
NET AMT
|
$990.00
|
|
|
|
|
ACRN AB Funded Amount
|
|
$990.00
|
FOB: Destination
|
|
|
|
|
|
ITEM NO
|
SUPPLIES/SERVICES
|
QUANTITY
|
UNIT
|
UNIT PRICE
|
AMOUNT
|
0003
|
|
1
|
Lot
|
$2,640.00
|
$2,640.00
|
|
|
Design Costs
FFP
Design Costs: 95% Submittal due from contractor 2 weeks from issuance of NTP to 95%. 100% Submittal due from contractor 1 week from issuance of NTP 100%. Government shall complete its technical evaluations of the submittals 2 weeks after receipt.
NSN: Z199-95-CES-MACC
MILSTRIP: FQ469043070402
PURCHASE REQUEST NUMBER: FQ4690430704
SIGNAL CODE: A
|
|
|
|
|
|
|
|
|
|
|
|
|
NET AMT
|
$2,640.00
|
|
|
|
|
ACRN AB Funded Amount
|
|
$2,640.00
|
Note: Section E modified for this example.
Note: Section F modified in this example.
Note: Section G modified in this example.
Section J - List of Documents, Exhibits and Other Attachments
Exhibit/Attachment Table of Contents
DOCUMENT TYPE
|
DESCRIPTION
|
PAGES
|
DATE
|
Attachment 1
|
Task Order
|
3
|
|
Attachment 2
|
SOW
|
1
|
|